S.NO | DESCRIPTION OF WORK | NAME OF EMPLOYEE | PROJECTS NAME | DATE OF START |
---|---|---|---|---|
1 | Plunger colunn | MMRC, Mumbai | Larsen &Toubro Limited Construction | Sep-17 |
2 | Micropiling Work | NTPC Koldam | Bumi Geoengineering ltd | May-17 |
3 | Slope Protection work | Sobha bela Encosta | Sobha limited | Mar-17 |
4 | Micropiling, Consolidation grouting, soil nailing, shotcreting | Tata Steel, jamshedpur | Larsen &Toubro Limited Construction | Mar-16 |
COMPLETED PROJECTS
S.NO | DESCRIPTION OF WORK | NAME OF EMPLOYEE | PROJECTS NAME | DATE OF START | DATE OF COMPLETION |
---|---|---|---|---|---|
1 | Consolidation grouting work | Nuclear power plant corporation of india limited | RS development and construction private ltd. | Aug-16 | May-17 |
2 | a) Curtain permeation grouting for the construction of coffer Dam-Tube a Manchette (TAM) Methode b) Consolidated grouting work | Bhasmey electric Project, Sikkim | Simplex Infrastructures limited | Oct-16 | Feb-17 |
3 | Consolidation grouting work | Fast Reactor Fuel cycle Facility -FRFCF (IGCAR) Project | Larsen & Toubro Limited | May-16 | Sep-16 |
4 | Core Drilling works for Geotechnical Investigation | Fast Reactor Fuel cycle Facility -FRFCF (IGCAR) Project | Larsen & Toubro Limited | Apr-16 | Jun-16 |
5 | Micro pilling Work | NTPC Koldam HP Project | ITD Cementation India Ltd | Apr-16 | Aug-16 |
6 | Curtain permeation grouting for the construction of Up stream coffer Dam-Tube a Manchette (TAM) Methode | Bajoli Holi Hydroelectric Project | Gammon India Limited | Jan-16 | Aug-16 |
7 | Drilling And cement Grouting for Tunnel- 4 (P1)-Tam Grouting-Tube a Manchette (TAM) Methode | Four Laning of Kiratpur Ner- Chowk Section of NH-21 | IL & FS Engineering Services | Dec-15 | Dec-15 |
8 | Drilling for Cable Anchor | Foundation Base of Flag Mast Pole at Pahari Mandir, Ranchi | M/S. Fressinet | Dec-15 | Dec-15 |
9 | Pipe Roofing for Tam Grouting for Cross passage | DMRC-CC-24 Project, Delhi | Geosmart Engineering Pvt LTD | Jan-15 | Oct-16 |
10 | Drilling for Cable Anchor | Emmami Tejomaya -Chennai | Sanfield (India) Limited | Sep-15 | - |
11 | Pile Drilling Work | Thekkalkot, Bellary- Karnataka | Ganges International Pvt Ltd(Solar) | Jan-15 | - |
12 | Pile Drilling Work | Siruguppa,Bellary- Karnataka | Yukth energy Solutions | Oct-14 | Jan-15 |
13 | Soil nailing for repairing of R.E wall | Ranchi ring Road project, Ranchi, Jharkhand | M/S.Elsamax Maintaince service Limited | Dec-13 | Jan-15 |
14 | ODEX Drilling for anchoring at Plunge Pool | Koldam Hydroelectric power Project , H.P | M/S. Italian-Thai Development Public Company Limited | Jan-13 | Mar-14 |
15 | Drilling works for Additional instruments and Piezometers | Koldam Hydroelectric power Project, H.P | M/S. Italian-Thai Development Public Company Limited | Nov-13 | May-14 |
16 | Drilling for Cable Anchor | EConstruction of additional office complex for supreme court project, New Delhi | M/S. Fressinet | Apr-13 | May-14 |
17 | Slope stabilization work by rock bolt, Ground anchor and shotcrete | Kalkaji mandir station,DMRC Project delhi | M/S.FEMC- Pradhibha-JV | Apr-13 | Jun-14 |
18 | Slope stabilization work by rock bolt, and shotcrete,, | Vasantha Vihar metro station, DMRC project Delhi | M/S. Larsen & Toubro | Mar-13 | May-14 |
19 | Drilling for inclined cable anchor | Residence complex of Lodha Builders, Wadala, Mumbai | M/S. ITD CEM | Jun-13 | - |
20 | Drilling for consolidation grouting at right bank of dam area, | PHEP-1 ,BHUTAN | M/S. Larsen & Toubro | Apirl-14 | Dec-13 |
21 | Underground drilling work for Deep curtain grouting, Drilling at plunge pool and Quartz quarry for Blasting and Instrument and Piezometer hole, | Koldam Hydroelectric power Project , H.P | M/S. ITD Cementation Pvt Ltd | Sep-07 | Oct-12 |
22 | Tam grouting, consolidation and contact grouting, deep curtain grouting | Parvathi Hydro power project-Stage-III, Sanju H.P | M/S Larsen& Toubro Limited | Mar-09 | May-12 |
23 | Drilling for Deep curtain grouting | Leakage during impounding of Dam and Power house at chamera–III HEP, H.P | M/S. HCC | Feb-12 | Dec-13 |
24 | Drilling and casting of 250 mm Tension pile | Majestic Metro station Bangalore for BMRC | M/S. Costal Projects Pvt Ltd | Mar-12 | Oct-12 |
25 | Soil nailing work | TATA MINES, DCMP joda project, odisha | M/S. Reinforced Earth india PVT Ltd | Apr-12 | Dec-13 |
26 | Drilling for Inclined Cable Anchor | Majestic Metro station Bangalore for BMRC | M/s. VSL India PVT Limited | Jun-12 | Aug-12 |
27 | Drilling for Inclined Cable Anchor | DLF Building at Egmore ,Chennai | M/S. Sanfield (india) Limited | Jun-12 | Apr-12 |
28 | Soil cement column installation | Dhanbhad water supply project Under Jn Nurm, SINDRI, Jharkhand | M/S Larsen& Toubro Limited | Jan-12 | Apr-12 |
29 | Solider pile, King post, Secant pile for station Building | BMRC Project. Bangalore | M/s. Soma Enter prizes | Mar-11 | Nov-12 |
30 | Drilling for Permanent anchor Bar in underground power house | DHEP, Bhutan | M/S. HCC | Oct-11 | Feb-12 |
31 | Under ground drilling work for Deep curtain grouting | Koldam Hydroelectric power Project , H.P | M/S Bumi Geo | Mar-10 | Dec-12 |
32 | Under ground drilling work for Deep curtain and Tam grouting | Koldam Hydroelectric power Project , H.P | M/s ITD cementation | Jul-10 | Nov-10 |
33 | Sand column at Casting Yard, Vanagaram | Chennai Port-Maduravoyal Expressway, Chennai | M/s. Soma Enter prizes | Oct-10 | Dec-09 |
34 | Solider pile for cut and cover of metro station | Race course, jorbagh, INA, AIIMS Metro station DMRC Project,Delhi | M/s. Soma Enter prizes | Apr-08 | Feb-09 |
35 | Under ground drilling work for Deep curtain grouting and Drilling for Blast hole & Drainage hole | Koldam Hydroelectric power Project , H.P | Right tunnelling and Co., Ltd | Dec-04 | Feb-05 |
36 | Drilling and Excavation | Kudankulan nuclear power project, Kudankulam, TN | M/S.HCC | Jul-03 | May-14 |
37 | Ramming, Drilling for solar foundation | Gujarat Rajasthan, U.P, TN, Orisha, Telegana | M/S L&T, ,Sterling &Wilson, Sun Edison, Chemtools, Yukta Energy (p) Ltd, M/s. Ganges Internationally Pvt. Ltd. | Mar-11 | - |
* Project No. 17 to 37 we are Involved for getting order,Providing technical support, deploying manpower,planning , Execution and completion of the Work